Dunes Hotel Al Barsha
CASE STUDY
Facility details
• Member since June 2013
• Architectural Structure: 2B + G + 14 Floors
(Hotel Apartment)
• Total built up area of 162, 982 sq ft
• Key assets:
2 Centralized Air Cooled Chillers
3 Primary pumps
1 Fresh Air Handling Units
• Operating Hours: 24 hours
Monthly Energy Savings
The chart below shows the actual kWh consumption plotted
against expected kWh and the monthly percentage savings
achieved after the implementation of Energy Conservation
Measures.
Emirates Energy Star (EES) team surveyed the building and proposed to provide real time remote
monitoring and control of the HVAC equipment from Pacific Controls 24x7 Global Command
Control Center with objective of optimizing energy consumption in the building and hence
reduce electricity bill.